Case Studies
We partner as embedded operators—not advisors—to de-risk delivery, protect margin, and accelerate schedules. Below are representative engagements across preconstruction, project controls, and field operations, with hard performance deltas.
Impact at a Glance
Preconstruction Wins
-
Hit rate up +22% after bid/no-bid gates
-
Estimate variance cut to ≤ ±5% @ 60-day
-
Concept-to-budget cycle time –35%
Field & Schedule Reliability
-
PPC/look-ahead adherence ≥ 90%
-
Recovery plans deployed in <10 days
-
Closeout punch duration –40%
Financial Controls
-
Forecast accuracy ≤ ±3–5%
-
Avoidable margin slippage –30%
-
CO TAT (event→executed) –50%

Main Street Builders
Operating Partner Turnaround
Context: Grassroots GC, ~$5–8M run-rate, fragmented workflows.
Mandate: Stand up program-grade controls and stabilize backlog.
​
What We Did :
-
Instituted bid/no-bid gates and a price-to-win model.
-
Deployed portfolio WBS, cost codes, and CPI/SPI dashboards.
-
Built superintendent look-ahead cadence; daily production tracking.
​​
Results (KPIs):
-
Qualified hit rate +19% in two quarters.
-
Forecast accuracy tightened to ±5% @ 60/90-day.
-
Schedule reliability (PPC) from 62% → 91%.
​​
Artifacts: Bid room playbook, P6/MSP templates, Power BI exec pack.
Contract Model: Monthly retainer (Operating Partner), value-based.